Compliance Radar
Who was sanctioned, and for what?
Fines, court rulings and incidents from Europe, North America, Latin America, Asia-Pacific, Middle East and Africa: 2,229 cases from 44 jurisdictions, each with an official source and checked against that source before publication. Filter by country, area of law and sector. Click a chart to drill down one level.
Click a bar to drill down one level.
Where?
by authority- British Columbia Securities Commission (BCSC), Executive Director (Vergleich und Anordnung) €2.11m 81 % · 1 case
- WorkSafeBC (Workers' Compensation Board of British Columbia) €388,782 15 % · 2 cases
- British Columbia Securities Commission (BCSC), Executive Director (Vergleich) €102,539 4 % · 2 cases
What for?
by area of lawAll areas of law
Who?
by sectorAll sectors
When?
per quarter, by date of decision| Period | Cases | Total |
|---|---|---|
| Q4 2023 | 0 | – |
| Q1 2024 | 0 | – |
| Q2 2024 | 0 | – |
| Q3 2024 | 0 | – |
| Q4 2024 | 1 | €40,623 |
| Q1 2025 | 0 | – |
| Q2 2025 | 1 | €2.11m |
| Q3 2025 | 1 | €61,916 |
| Q4 2025 | 2 | €388,782 |
| Q1 2026 | 0 | – |
| Q2 2026 | 0 | – |
| Q3 2026 | 0 | – |
| Q4 2026 | 0 | – |
5 cases
12 Dec 2025 EllisDon CorporationEllisDon: CAD 514,831.53 penalty after fatal crane incident at high-rise site €318,998
In February 2024 a flytable was being moved by tower crane at the Oakridge Park construction site; as it was pushed out it accelerated out of the building, fell and fatally struck a worker. WorkSafeBC found that EllisDon, as prime contractor, had not regularly reviewed the subcontractor's safe work procedures, had not confirmed that a risk assessment had been carried out, had not classed the lift as critical, had not ensured written lift plans, had not controlled the exclusion zone on the ground and had not coordinated the health and safety activities of the employers involved. It imposed an administrative penalty of CAD 514,831.53.
Prime contractors must actively plan, review and coordinate their subcontractors' critical crane lifts rather than relying on their procedures.
Coordinating health and safety and critical lifts on multi-employer construction sites
- Authority / court
- WorkSafeBC (Workers' Compensation Board of British Columbia)
- Area of law
- Health and safety and employment law · Workplace safety and accidents
- Legal basis
- Arbeitsschutzvorschriften von British Columbia, insbesondere Occupational Health and Safety Regulation (OHSR) – Pflichten des Hauptauftragnehmers (prime contractor) und Anforderungen an kritische Kranhübe; Verwaltungsstrafe (administrative penalty) von WorkSafeBC
- Action
- Fine
- Status of proceedings
- unknown
- Sector
- Construction and real estate
- Published
- 12 Dec 2025
Original amount 514,831.53 CAD, converted at the ECB reference rate of 12 Dec 2025.
Checked against the official source on 3 Oct 2026 · Direct link
Report an error
12 Dec 2025 Newway Concrete FormingNewway Concrete Forming: CAD 112,624.66 penalty after fatal flytable incident €69,784
In February 2024 the formwork contractor was moving a flytable by tower crane at the Oakridge Park construction site when it fell out of the building and fatally struck a worker. WorkSafeBC found, among other things, missing written lift plans for critical lifts, inadequate procedures for corner flytables, a lack of risk assessments and inspections, loads being passed over people and insufficient instruction, training and supervision of workers, and imposed an administrative penalty of CAD 112,624.66.
Formwork and lifting crews need written step-by-step procedures, trained ground control workers and controlled exclusion zones.
Safe lifting and formwork operations, training of ground control workers
Missing or inadequate training played a role in the decision.
- Authority / court
- WorkSafeBC (Workers' Compensation Board of British Columbia)
- Area of law
- Health and safety and employment law · Workplace safety and accidents
- Legal basis
- Arbeitsschutzvorschriften von British Columbia, insbesondere Occupational Health and Safety Regulation (OHSR) – Hebepläne, Schalungsarbeiten, Unterweisung und Aufsicht; Verwaltungsstrafe (administrative penalty) von WorkSafeBC
- Action
- Fine
- Status of proceedings
- unknown
- Sector
- Construction and real estate
- Published
- 12 Dec 2025
Original amount 112,624.66 CAD, converted at the ECB reference rate of 12 Dec 2025.
Checked against the official source on 3 Oct 2026 · Direct link
Report an error
22 Aug 2025 Global Crossing Airlines Group Inc. (ehemals Canada Jetlines Ltd.)Canada Jetlines (now Global Crossing Airlines): CAD 100,000 over late disclosure €61,916
On 22 February 2018 the then start-up airline told the Canada Transportation Agency that, after a letter of intent for two leased aircraft had been terminated, the start of flight operations would slip to the end of 2018, but it did not publish this material change until 13 March 2018. In its settlement with the BCSC the company admitted breaching the duty of immediate disclosure and pays CAD 100,000 as a joint payment. Measures against individuals are not set out here.
A material change in plans reported to another authority must be disclosed to the capital market at the same time.
Timely disclosure of material changes
- Authority / court
- British Columbia Securities Commission (BCSC), Executive Director (Vergleich)
- Area of law
- Capital markets and financial supervision · Disclosure and reporting obligations
- Legal basis
- Securities Act (British Columbia), RSBC 1996, c. 418, s. 85 (unverzügliche Offenlegung wesentlicher Änderungen) und s. 168.2(1)
- Action
- Fine
- Status of proceedings
- final
- Sector
- Transport, logistics and shipping
- Liability of senior managers
- Measures against individuals are not set out here.
- Published
- 22 Aug 2025
Original amount 100,000 CAD, converted at the ECB reference rate of 22 Aug 2025.
Checked against the official source on 3 Oct 2026 · Direct link
Report an error
16 Apr 2025 NetCents Technology Inc.NetCents Technology: CAD 3.34m disgorgement over misleading crypto coin sale €2.11m
In 2017 the Vancouver payment processing company sold its own crypto coin to about 500 investors without a prospectus, raising CAD 3,341,040.91; in doing so it referred to an independent non-profit organisation that did not exist, announced sold-out tranches that had not sold out and cited inflated monthly revenue. It also operated an unrecognised exchange for the coin. Under its settlement with the BCSC, NetCents was permanently barred from trading in securities and must pay the proceeds, frozen since 2018, together with interest to the Commission. The amount of CAD 3,341,040.91 is a disgorgement of the proceeds, not an administrative penalty.
Anyone selling crypto tokens to investors must check securities law obligations and may only make verifiable statements in white papers and announcements.
Token sales as securities offerings and truthful investor information
- Authority / court
- British Columbia Securities Commission (BCSC), Executive Director (Vergleich und Anordnung)
- Area of law
- Capital markets and financial supervision · Disclosure and reporting obligations
- Legal basis
- Securities Act (British Columbia), RSBC 1996, c. 418, s. 61 (Prospektpflicht), s. 50(1)(d) (Falschangaben), s. 25 (nicht anerkannte Börse); Anordnungen nach s. 161(1)(b), (d) und (g)
- Action
- Disgorgement of profits
- Status of proceedings
- final
- Sector
- Financial services and insurance
- Repeat case
- no
- Mitigating circumstances
- The directors and officers at the time have all left the company; the settlement made a hearing unnecessary.
- Published
- 16 Apr 2025
Original amount 3,341,040.91 CAD, converted at the ECB reference rate of 16 Apr 2025.
- BCSC: Order, NetCents Technology Inc., 2025 BCSECCOM 140, 16.04.2025 Decision of an authority
- BCSC: Settlement Agreement, NetCents Technology Inc., 2025 BCSECCOM 139 Decision of an authority
Checked against the official source on 3 Oct 2026 · Direct link
Report an error
28 Nov 2024 WealthBar Financial Services Inc. (CI Direct Investing)CI Direct Investing (WealthBar): CAD 60,000 over KYC and conflict-of-interest failings €40,623
A 2022 conflicts-of-interest sweep by the Canadian Securities Administrators found that, after the Client Focused Reforms took effect, the online portfolio manager had failed to identify and disclose conflicts arising from referral arrangements with twelve partners, assessed clients referred through four of those partners only for those partners' model portfolios and did not meet its know-your-client obligations because its online questionnaire was incomplete. Under its settlement with the BCSC, WealthBar undertook to pay CAD 60,000; it had previously paid CAD 14,800 in examination costs and retained an independent compliance monitor for one year.
New rules such as the Client Focused Reforms require an active reassessment of existing partnerships, questionnaires and advice processes.
Conflicts of interest, suitability and know-your-client in digital wealth management
- Authority / court
- British Columbia Securities Commission (BCSC), Executive Director (Vergleich)
- Area of law
- Capital markets and financial supervision · Organisational requirements
- Legal basis
- National Instrument 31-103, s. 13.2, 13.2.01 (Know your Client), 13.3 (Eignung), 13.4 (Interessenkonflikte); Securities Act (British Columbia), RSBC 1996, c. 418
- Action
- Fine
- Status of proceedings
- final
- Sector
- Financial services and insurance
- Mitigating circumstances
- Early settlement, cooperation during the examination and the proceedings, no investor complaints; the deficiencies were remedied under the oversight of a compliance monitor.
- Published
- 28 Nov 2024
Original amount 60,000 CAD, converted at the ECB reference rate of 28 Nov 2024.
Checked against the official source on 3 Oct 2026 · Direct link