Compliance Radar
Who was sanctioned, and for what?
Fines, court rulings and incidents from Europe, North America, Latin America, Asia-Pacific, Middle East and Africa: 2,229 cases from 44 jurisdictions, each with an official source and checked against that source before publication. Filter by country, area of law and sector. Click a chart to drill down one level.
Click a bar to drill down one level.
Where?
by levelWhat for?
by topicWho?
by company- Anonymised companies €168,543 100 % · 1 case
When?
per quarter, by date of decision| Period | Cases | Total |
|---|---|---|
| Q4 2023 | 0 | – |
| Q1 2024 | 0 | – |
| Q2 2024 | 0 | – |
| Q3 2024 | 0 | – |
| Q4 2024 | 1 | €168,543 |
| Q1 2025 | 0 | – |
| Q2 2025 | 0 | – |
| Q3 2025 | 0 | – |
| Q4 2025 | 0 | – |
| Q1 2026 | 0 | – |
| Q2 2026 | 0 | – |
| Q3 2026 | 0 | – |
| Q4 2026 | 0 | – |
1 case
19 Nov 2024 an electricity grid operator in OntarioGrid operator: CA$250,000 after contact with a live line €168,543
While copper conductors were being installed on a de-energised 44 kV line, a piece of conductor touched the uncovered 4.8 kV line running below it; a worker was seriously injured. The grid operator had not complied with the safety rules for work near energised equipment. Fine of CA$250,000 against the company (19 November 2024).
De-energising alone is not enough; adjacent lines that remain live must be covered.
Covering adjacent live parts
- Authority / court
- Provincial Offences Court Goderich (Ermittlung: Ontario Ministry of Labour, Immigration, Training and Skills Development)
- Area of law
- Health and safety and employment law · Workplace safety and accidents
- Legal basis
- Sections 181, 183 O. Reg. 213/91 (Construction Projects) i. V. m. s. 132 Electrical Utility Safety Rules; ss. 27(1)(a), 25(1)(c) Occupational Health and Safety Act (Ontario)
- Action
- Fine
- Status of proceedings
- final
- Sector
- Energy and utilities
- Mitigating circumstances
- Guilty plea.
- Liability of senior managers
- Measures against individuals are not reported here.
- Published
- 15 Jan 2025
Original amount 250,000 CAD, converted at the ECB reference rate of 19 Nov 2024.
- Ontario Newsroom, Court Bulletin zu Hydro One Networks Inc. (Entscheidung 2024) Press release of an authority
Checked against the official source on 28 Sep 2026 · Version 3 · Company name anonymised since 19 Nov 2026 · Direct link